US 12 Rehabilitation

Walworth County

County H Intersection

Project Limits

County H Intersection with US 12 – Genoa City

Improvements

  • Replace pavement in the intersection
  • Add monotube traffic signals
  • Replace culvert piping that crosses County H

Traffic Impacts

County Road H is open to single-lane traffic in each direction.

What to Expect

Stage 1 to start on April 20th until approximately May 15th. Work to include:

  • New storm sewer installation
  • Concrete masonry end wall installation
  • Asphalt base patching and temporary asphalt

Stage 2

  • Start work on new traffic signals
  • Complete asphalt widening, milling and paving on the outside lanes of County H

Stage 3A

  • Continue work on traffic signals
  • Complete widening and concrete curb and gutter on inside lanes of County H east of US 12 off ramp
  • Complete widening, milling and paving of east side of US 12 off ramp
  • Complete milling and paving of inside lanes of County H east of US 12 off ramp

Stage 3B

  • Finish work on traffic signals
  • Complete widening and concrete curb and gutter on inside lanes of County H west of US 12 off ramp
  • Complete widening, milling and paving of west side of US 12 off ramp
  • Complete milling and paving of inside lanes of County H west of US 12 off ramp

Schedule

Late April to early fall