Latest News

Latest Traffic Report: 2/20/17

List of all scheduled closures and restrictions on the Zoo Interchange Project from February 20 – February 26:

Monday (2/20)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– there will be a full closure 6am through 2/27 Deer Creek Trail NB/SB at I-94 for bridge demolition.

– lanes will be closed overnight I-41 SB from Burleigh St to Center St for fence screening.   – this work has been cancelled due to contractor coordination

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for overhang work.   *contingency is Tuesday 2/21

– there will be a full closure overnight I-41 SB at Bluemound Rd for overhang work.   *contingency is Tuesday 2/21

 

Tuesday (2/21)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– lanes will be closed overnight I-41 SB from Burleigh St to Center St for fence screening.

– a lane will be closed overnight I-41 NB from the Zoo Interchange to Bluemound Rd for barrier wall work.

– there will be a full closure overnight I-94 WB at the Zoo Interchange for bridge demolition and barrier wall work.   *contingency is Wednesday 2/22

– there will be a full closure overnight I-94 EB at Moorland Rd for bridge demolition and barrier wall work.   *contingency is Wednesday 2/22

– the Zoo Int N-W system ramp will be closed overnight for barrier wall work.

– the Zoo Int S-W system ramp will be closed overnight for barrier wall work.

 

Wednesday (2/22)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– lanes will be closed overnight I-41 SB from Burleigh St to Center St for fence screening.

– there will be a full closure overnight I-94 EB at HWY 100 for decking and overhang work.

 

Thursday (2/23)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– there will be a full closure 6am through 3/3 Deer Creek Trail NB/SB at I-94 for bridge demolition.

– lanes will be closed overnight I-41 SB from Burleigh St to Center St for fence screening.

– there will be a full closure overnight I-94 EB at HWY 100 for a deck pour.   *contingency is Friday 2/24

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for a deck pour.   *contingency is Friday 2/24

– there will be a full closure overnight I-41 SB at Bluemound Rd for a deck pour.   *contingency is Friday 2/24

– the Zoo Int S-E system ramp will be closed overnight for barrier wall work.

 

Friday (2/24)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– there will be a full closure 2/23 through 3/3 Deer Creek Trail NB/SB at I-94 for bridge demolition.

– there will be a full closure overnight I-94 EB at HWY 100 for decking and overhang work.

– there will be a full closure overnight I-94 WB at 84th St for sign structure removal.   *contingency is Thursday 2/23

 

Saturday (2/25)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– there will be a full closure 2/23 through 3/3 Deer Creek Trail NB/SB at I-94 for bridge demolition.

 

Sunday (2/26)

Zoo Interchange Project

– there will be a full closure 2/13 through 2/27 100th St NB/SB at Schlinger Ave for crane mobilization.

– there will be a full closure 2/23 through 3/3 Deer Creek Trail NB/SB at I-94 for bridge demolition.

 

Long-Term Closures

Zoo Interchange Project

– there will be a full closure of Fairview Ave WB from 116th St to Curtis Rd through Spring 2017 for retaining wall construction (local access maintained).

– there will be a full closure of Fairview Ave EB from 118th St to 116th St through Spring 2017 for retaining wall construction (becomes one-way WB only).

– there will be a full closure of the Zoo Int W-N system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of the Zoo Int N-E system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of Wisconsin Ave EB/WB from 95th St to 97th St through late May 2017 for reconstruction.

– there will be a full closure of the Bluemound Rd entrance ramp to I-41 SB through late August 2017 for ramp reconstruction.

– there will be a full closure Elm Grove Rd NB/SB at I-94 through late August 2017 for bridge reconstruction.

– there will be a full closure of the Lincoln Ave entrance ramp to I-41/894 NB through early Fall 2017 for roadway construction.

– there will be a full closure of the Greenfield Avenue entrance ramp to I-41/894 SB through early Fall 2017 for roadway construction.

– a lane will be closed on Curtis Rd NB/SB under I-94 through Fall 2017 for roadway construction.

– there will be a full closure of the HWY 100 entrance ramp to I-94 WB through Fall 2017 for ramp reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 NB through late November 2017 for roadway reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 SB (from I-94 WB and I-41/894 NB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Zoo Int E-S system ramp through late November 2017 for ramp reconstruction.

– there will be a full closure of the I-94 EB exit ramp to 84th St (from I-94 EB and I-41 SB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB (to I-41 NB and I-94 WB) through late 2017 for ramp reconstruction.

– there will be a full closure of the Oak Leaf Trail NB/SB at I-94 through late 2017 for bridge demolition.

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through late April 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through early Summer 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through early Summer 2018 for roadway construction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through early Summer 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through early Summer 2018 for project construction.