Latest Traffic Report: 1/20/17

List of all scheduled closures and restrictions on the Zoo Interchange Project from January 20 – January 29:

Friday (1/20)

Zoo Interchange Project

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for decking.   *contingency is Tuesday 1/24

– there will be a full closure overnight I-41 SB at the Zoo Interchange for decking.   *contingency is Tuesday 1/24

 

Saturday (1/21)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (1/22)

Zoo Interchange Project

– only long-term closures in effect.

 

Monday (1/23)

Zoo Interchange Project

– a lane will be closed overnight I-94 WB east of Moorland Rd for Waukesha Co Maintenance beam guard repair.

– a lane will be closed overnight I-94 WB from 92nd St to the Zoo Interchange for barrier wall work.

– a lane will be closed overnight I-41 NB from Bluemound Rd to Wisconsin Ave for barrier wall work.

– a lane will be closed overnight I-94 EB from the Zoo Interchange to for 92nd St decking.

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for decking.   *contingency is Tuesday 1/24

– there will be a full closure overnight I-41 SB at the Zoo Interchange for decking.   *contingency is Tuesday 1/24

 

Dousman Rd/Golden Lake Rd/I-94 Project

– a lane will be closed overnight I-94 EB at Golden Lake Rd for mill and fill.

 

Tuesday (1/24)

Zoo Interchange Project

– a lane will be closed overnight I-94 EB from the Zoo Interchange to for 92nd St decking.

– there will be a full closure overnight I-94 WB at 84th St for decking.   *contingency is Thursday 1/26

– the Zoo Int S-E system ramp will be closed overnight for equipment mobilization.

 

Wednesday (1/25)

Zoo Interchange Project

– a lane will be closed overnight I-94 EB from the Zoo Interchange to for 92nd St decking.

– there will be a full closure overnight I-94 WB at 84th St for a traffic switch and decking.   *contingency is Thursday 1/26

 

Thursday (1/26)

Zoo Interchange Project

– a lane will be closed overnight I-94 EB from the Zoo Interchange to for 92nd St decking.

 

Friday (1/27)

Zoo Interchange Project

– only long-term closures in effect.

 

Saturday (1/28)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (1/29)

Zoo Interchange Project

– only long-term closures in effect.

 

Long-Term Closures

Zoo Interchange Project

– there will be a full closure of Fairview Ave WB from 116th St to Curtis Rd through Spring 2017 for retaining wall construction (local access maintained).

– there will be a full closure of Fairview Ave EB from 118th St to 116th St through Spring 2017 for retaining wall construction (becomes one-way WB only).

– there will be a full closure of the Zoo Int W-N system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of the Zoo Int N-E system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of Wisconsin Ave EB/WB from 95th St to 97th St through late May 2017 for reconstruction.

– there will be a full closure of the Bluemound Rd entrance ramp to I-41 SB through late August 2017 for ramp reconstruction.

– there will be a full closure of the Lincoln Ave entrance ramp to I-41/894 NB through early Fall 2017 for roadway construction.

– there will be a full closure of the Greenfield Avenue entrance ramp to I-41/894 SB through early Fall 2017 for roadway construction.

– a lane will be closed on Curtis Rd NB/SB under I-94 through Fall 2017 for roadway construction.

– there will be a full closure of the HWY 100 entrance ramp to I-94 WB through Fall 2017 for ramp reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 NB through late November 2017 for roadway reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 SB (from I-94 WB and I-41/894 NB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Zoo Int E-S system ramp through late November 2017 for ramp reconstruction.

– there will be a full closure of the I-94 EB exit ramp to 84th St (from I-94 EB and I-41 SB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB (to I-41 NB and I-94 WB) through late 2017 for ramp reconstruction.

– there will be a full closure of the Oak Leaf Trail NB/SB at I-94 through late 2017 for bridge demolition.

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through late April 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through early Summer 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through early Summer 2018 for roadway construction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through early Summer 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through early Summer 2018 for project construction.